Aakash Ganga
Status
:  
Under way
Project Period
:  
20 Aug 2017  to   13 Dec 2018
Partner
:  
SITI and BCT
Villages Covered
:  
1
Gram Tankas
:  
0
Griha Tankas
:  
7
Total Area for Horticulture (Sq.meters)
:  
0
Total Tanka Capacity (Liters)
:  
150,080
Project Cost (Rs)
:  
4,500,000
Funding :
NameFund Amount (Rs)Remarks
Sustainable Innovations US 453,254 Aakash Ganga Social Enterprise
Sustainable Innovations US 906,509 2nd Installment
Location
Gram Tanka
Griha Tanka
Villages Covered :
 DistrictBlockVillageGram TankaCompleted Gram TankaGram Tanka Capacity (Liters)Griha TankaCompleted Griha TankaGriha Tanka Capacity (Liters)Community Land (Sq.meters)
Jhunjhunu Buhana Sanwlod 0 0 0 7 7 150,080 0
Model Project Cost/ Estimate :
No record found.
Related Documents :
Title Report Date Uploaded On
Engineering Designs (Raila) 13 Jun 2018 13 Jun 2018
Land Lease Agreement 13 Jun 2018 13 Jun 2018
Sanwlod (Mapbook) 04 Sep 2017 13 Jun 2018
Mapbook (Khanpur) 17 Oct 2017 13 Jun 2018
Blue print 29 Mar 2020 29 Mar 2020
Uploaded Bills:
Month Total BillUploaded Bill
February 3 3